Back to case studies
Botley Station, Oxford
17 April 2019
The modelling of the S&C at Botley Station to incorporate a new track layouts and drainage system required 350m of 6ft collector drainage together with 24m of carrier drain UTX, 7 in line GRP TerraPits and a 90 degree TerraPit. The installation ran towards Southampton from the platform turning to cross the track (right) under the S&C into the siding 10ft running to the out fall.
From order to completion of delivers was 4 weeks.
Download PDF