Ipswich Station

4 July 2019

Following the building of a new viaduct at Ipswich, new routes under the railway had to be found for Telecom’s & East Anglia Water mains. It was decided to use non-dig technology to drill and sleeve through the embankment 12m apart to enable both companies to get their supplies through.

A launch pit and reception pit had to be made ready, then Molegrove drilled through the embankment supporting each metre with a 560mm OD steel casing ensuring the track was supported at all times. The railway line remained open for traffic throughout the installation. 

Download PDF

More case studies

Carstairs Rail Project, Glasgow

3 June 2020

MGS has supplied a Pagani TG63-150 for use in a large-scale infrastructure SI project near Glasgow to investigate a railway embankment up to 10m in height which had instability issues.

read more

TerraDrain installed at Bletchingley

10 March 2020

Demco’s specialist track drainage pipe TerraDrain 11 has been installed as part of upgrade works at Bletchingley Tunnel in Surrey. TerraDrain was used because it is approved for installation at

read more

Southampton Station

4 July 2019

The modelling of the S&C at Southampton Station to incorporate a new track layout and drainage system. The project required 200m of 6ft TerraDrain collector drainage together with 12m of

read more

REGISTERED OFFICE: Geotechnical Centre, Rougham Industrial Estate, Rougham, Bury St Edmunds, Suffolk IP30 9ND. Registered in England: 2481929